How HFE Company works go in this February

Date:2021-02-27 11:45 Click: BigNormalSmall

    As of February 27, the projects India Godda power plant, SS Power I, BJCEEE Shanxi Jinmao Energy Technology, BJCEEE Henan Liyuan New Energy Technology, Qilu Yellow River Bridge, Phoenix Yellow River Bridge Approach Span, Zhan-Lin Road and Zhong-Kai Express Way contracted by HFE have progressed as follows:
    I   Godda power plant
    1. Drawing: to date, for a total of 46430 tons, the drawings have been received and distributed.
    2. For rivet welding, 46430 tons completed; for paint application, 46430 tons completed.
    3. For packing, 46310 tons completed; for delivery, 45736 tons completed.
    II       SS Power I 2x660MW coal fired power plant
    1. Drawing: to date, for a total of 48000 tons, the drawings have been received and distributed.
    2. For rivet welding, 38700 tons completed; for paint application, 36400 tons completed.
    3. For packing, 35600 tons completed; for delivery, 34102 tons completed.
    III    BJCEEE Shanxi Jinmao Energy Technology
    1. Drawing: to date, for a total of 695 tons, the drawings have been received and distributed.
    2. For rivet welding, 373 tons completed; for paint application, 45 tons completed.
    IV       BJCEEE Henan Liyuan New Energy Technology
    1. Drawing: to date, for a total of 695 tons, the drawings have been received and distributed.
    2. For rivet welding, 558 tons completed; for paint application, 140 tons completed.
    V   Qilu Yellow River Bridge
    1. Drawing: to date, for a total of 13924 tons, the drawings have been received and distributed.
    2. For rivet welding, 13906 tons completed; for paint application, 12338 tons completed.            
    3. For packing, 12143 tons completed; for delivery, 12143 tons completed.
    VI       Phoenix Yellow River Bridge Approach Span
    1. Drawing: to date, for a total of 15101 tons, the drawings have been received and distributed.
    2. For rivet welding, 13375 tons completed; for paint application, 10884 tons completed.
    3. For delivery, 10605 tons completed.
    VII    Zhan-Lin Road
    1. Drawing: to date, for a total of 16879 tons, the drawings have been received and distributed.
    2. For rivet welding, 2666 tons completed; for paint application, 188 tons completed.
    3. For packing, 68 tons completed; for delivery, 51 tons completed.
    VIII  Zhong-Kai Express Way
    1. For a total of 10644 tons, till now the drawings have been received where 7965 tons distributed totally.
    2. For rivet welding, 5170 tons completed; for paint application, 5170 tons completed.
    3. For delivery, 3075 tons completed.